PGE North Fork Dam
Project Details
Prime Contractor: Advanced American Construction
Owner: Portland General Electric
Location: Estacada, OR | April 2003 – November 2003
Owner: Portland General Electric
Location: Estacada, OR | April 2003 – November 2003
The project involved the installation of a 60-foot x 50-foot bulkhead dewatering system and the installation of new seals, sandblasting, and painting the three gates at Portland General Electric’s North Fork Dam on the Clackamas River.
Project Highlights
- Installation of 60-foot x 50-foot bulkhead dewatering system.
- Install new seals, sand-blast and paint three gates.
- Innovative bulkhead design and installation.
- Limited access requirement necessitated the use of a crane barge.