Nike MLS Soccer Barge

Prime Contractor: Advanced American Construction
Owner: Nike - Etzel Agency

Portland , OR
|
July 2014 - August 2014
« Previous ProjectNext Project »Back to Projects

Project Details

Advanced American Construction worked with Etzel Agency to assemble a 60' x 100' barge for Nike to host a soccer event on the Willamette River. AAC responded to a very short project time line and successfully met all of the owners goals. AAC assisted the project team with after hour operation to produce critical parts to ensure the project's success. The barge that AAC assembled successfully participated in a very public event on the river in downtown Portland.

Project Highlights

  • Assembled floats to create a 60' x 100' spud barge 
  • Installed scaffolding deck with plywood playing surface.  Assisted with installation and placement of paint, sound equipment, lighting and bleachers
  • Mobilized and placed barge in downtown Portland, OR
  • Provided event marine support
  • Demobilized and  disassembled all equipment and materials
  • Worked on a very short time line with an accelerated schedule

Project Photos

Stay Informed / Subscribe to our newsletter for the latest news, event invitations, and more!