Advanced American Construction was hired to furnish, splice and drive pipe pile to build the Tidewater Cove Marina, a private investment project in Vancouver, Washington. To meet the restrictions of the in-water work window and delays to the start of the project, AAC worked quickly and efficiently to meet all project goals within a tight timeframe. The project was completed ahead of schedule, on budget with superior quality and zero recordable injuries.

Project Highlights

  • Furnished and installed (45) new 24″ x .500 x 84′ pipe pile, (36) new 16″ x .500 x 80′ pipe pile all with caps.
  • Designed and fabricated an in-house pile driving template that resulted in a significant increase to the pile driving production rates; project start was delayed by 30-days and AAC recovered the schedule to meet the customer goal.