Bull Run Dam Tower 2 Improvement Project

Project Details

Prime Contractor: Advanced American Construction
Owner: City of Portland Water Bureau
Location: Sandy, OR | February 2012 – December 2014

AAC was the CM/GC for multiple phases to modify the north and south intake towers at Bull Run Tower 2 to improve fish habitat within the Bull Run River system. Modifications included installation of a selective withdrawal system on the north tower, new mechanical and electrical operating systems, water quality monitoring equipment, site civil improvements, and fish flow piping.

The pristine Bull Run Watershed is the source of drinking water for the City of Portland, so special care had to be taken throughout this project to ensure that water was not contaminated. The total contract value on this project was more than $30 million.

AAC won the AGC/Alliant 2014 Build America Award and the Daily Journal of Commerce 2014 Top Projects Award for the Bull Run project.

Project Highlights

  • 250-foot long temporary work trestle
  • 1,600 cubic yards of sediment removal
  • Install underwater concrete block revetment system
  • Concrete demolition
  • North Tower structural steel wet well and slide gates
  • Install pre-engineered electrical building
  • Mechanical and electrical systems installation
  • Fish flow piping installation
  • Over 14,000 AAC diver hours to complete the work. Drilled shaft, tangent pile wall, and secant pile wall installation. Steel piping installation up to 96″ diameter
1121-835

Project Awards

Award: 2014 AGC/Alliant Build America Award – Utility Infrastructure Renovation
Award: 2014 DJC Top Projects Award – Infrastructure