John Day Downstream Gate & Sheave Replacement

Project Details

Prime Contractor: Advanced American Construction
Owner: US Army Corps of Engineers
Location: Rufus, OR | October 2009 – March 2011

The Army Corps of Engineers (Portland District) issued notice to proceed to Advanced American Construction, Inc. (AAC) on October 8, 2009 for the Downstream Gate and Friction Sheave Replacement at the John Day Dam navigational lock. John Day Dam is located on the Columbia River near Rufus, Oregon, 2 hours east of Portland. The weight of the downstream gate was in excess of 2 million pounds. AAC removed and replaced the downsteam gate in four sections each, using a 660 ton barge mounted crane. Once loaded, the derrick barge was transported upriver to the John Day Dam to begin work. Replacement of the downstream gate required a 14 week navigational lock closure that began December 10, 2010. Due to the necessity of the river being closed in order to complete this work, AAC crews worked double shifts six and seven days per week.

In addition to replacing the navigational lock gate, AAC’s contract included replacement of the full mechanical drive system. Work included jacking the two, 1 million pound counterweights, removal of the wire ropes and replacement of the friction sheaves with a 300 ton crane from the dam.

Project Highlights

  • Replace 2.5 million pound structural steel gate.
  • Replace 2 each,18-foot diameter wire rope sheaves.
  • Jack 2 each, 1 million pound counterweights.
  • Complete replacement of mechanical friction sheave drive system.
  • All work performed within 14 week accelerated schedule.
  • Heavy Lift 
1121-835

Project Awards

Award: 2012 AGC/Alliant Build America Award – Federal & Heavy Renovation
Award: 2012 AGC/Alliant Marvin M. Black Excellence in Partnering Award
Award: 2012 AGC Build Washington – Top Heavy/Industrial Grand Award