Little Goose Dam Temporary Spillway Weir
Project Details
Prime Contractor: Advanced American Construction
Owner: US Army Corps of Engineers
Location: Starbuck, WA | October 2008 – March 2009
Owner: US Army Corps of Engineers
Location: Starbuck, WA | October 2008 – March 2009
The first of two projects at the Little Goose Dam, Advanced American Construction, Inc. (AAC) worked on an expedited timeline to fabricate, deliver and install several new components to the dam.
AAC provided 1 new weir and lifting beams, a closure gate, dogging beams, vent tubes, slot tubes, slot fillers and stop log. AAC partnered with Jesse Engineering, who fabricated the structural steel pieces in Tacoma, WA. They were then shipped by truck down I-5 to Vancouver, Washington where they were loaded onto a barge with the largest mobile harbor crane in North America. The barge traveled 280 miles upriver to Little Goose Dam for the final installation.
Project Highlights
- Fabricated & installed 25,000 pound stop log
- Fabricated & installed 120,000 pound weir assembly
- Fabricated & installed 96,000 pound closure gate
- All installations required a heavy lift crane barge