AAC was the CM/GC for multiple phases to modify the north and south intake towers at Bull Run Tower 2 to improve fish habitat within the Bull Run River system. Modifications included installation of selective withdrawal system on the north tower, new mechanical and electrical operating systems, water quality montoring equipment, site civil improvements and fish flow piping.
The pristine Bull Run Watershed is the source of drinking water for the City of Portland so special care had to be taken throughout this project to ensure that water was not contaminated. The total contract value on this project was more than $30 million.
AAC won the AGC/Alliant 2014 Build America Award and the Daily Journal of Commerce 2014 Top Projects Award for the Bull Run project.