Chinook Landing - Transient Dock Access & Replacement

Prime Contractor: Advanced American Construction
Owner: Metro

Fairview, OR
|
September 2020 - March 2021
« Previous ProjectNext Project »Back to Projects

Project Details


AAC dredged 11,000 CY of material and removed and replaced the existing pile and floating dock. In addition, a new ADA accessible concrete abutment and 80” gangway were installed for better access to the dock. With a limited work window and the small work area inside the marina, AAC modified the pile driving plan to use a land based crane. The dredging and pile driving had to happen simultaneously due to the fish windows. AAC used a 300-ton crane on shore to demo the old dock, install the new floats and drive the new pile.

The project was completed on time and on budget despite running into construction debris and large quantities of riprap while dredging in the marina.

Project Highlights

  • New Concrete Deck and Gangway with ADA accessibility
  • Dredging of the marina and marine entrance to allow access during all tides
  • 11,000 CY of material removed
  • Offshore disposal of material in designated site on the Columbia River
  • Demolition of existing dock
  • New landscaping

Project Photos