Project Details

The Terminal 1 – Vancouver Landing Structural Renovation Project is the initial phase of a project creating a green space at the existing amphitheater structure. This phase will renovate the structural lateral system to resist a code level seismic event through a batter pile system. The project adds two seismic dolphin structures integrated into the existing deck structure. Each dolphin will have 10 new steel batter piles and a new concrete pile cap. The project includes steel framing to the existing structure and modifies the top deck geometry for the future green space. The project removes the existing precast concrete amphitheater seating and a concrete bulkhead wall installing flat hollow core deck panels. The bulkhead wall will be replaced with a new concrete cutoff wall set at a lower elevation.

Project Highlights

  • Concrete Demolition
  • 20 EA - 24" Pipe Pile Driven
  • Structural Steel Retrofit
  • Structural Steel Installation
  • Precast Panel Installation
  • Cast-in-place Concrete Placement
  • Rip Rap & Earthwork
  • Steel Structure Coating

Project Photos